MASTER OF WORK |
A.I.D.E. B-4420 Saint-Nicolas |
GENERAL CONTRACTOR |
Société BAGON - Ingénieurs Conseils |
YEAR |
Start-up : 2001 |
PRESTATIONS |
Like sub-contractor for BAGON : direction of works
for the process lines |
CAPACITY OF TREATMENT |
600 |
E.H. |
108 |
m³/day |
32,4 |
kg BOD/day |
|
MAXIMUM PERMISSIBLE CONCENTRATION |
BOD |
: |
25 |
mg O2/l |
COD |
: |
125 |
mg O2/l |
Suspended solids |
: |
35 |
mg/l |
|
TREATMENT LINE |
· |
Preliminary settler, collecting tanks and
anaerobic reactor for sludge |
· |
Biological
treatment on "biodiscs" |
· |
Settling with plates |
|